Case Study Accelerated Time-to-Revenue for a 100MW ERCOT Battery Storage Project Share: Opens in a new window Opens in a new window Opens in a new window Copied to clipboard FlexGen’s One Touch Commissioning approach enabled a 100MW ERCOT BESS site to reach commercial operation months ahead of a smaller 10MW comparison project utilizing a different EMS platform Not all energy management systems (EMS) are created equal, especially when it comes to commissioning utility-scale battery energy storage projects. A major energy storage developer in Texas was simultaneously commissioning two projects with different EMS providers: a 100 MW / 200 MWh battery energy storage system supported by FlexGen and a smaller 10 MW project supported by another provider. Despite the difference in project size, both faced complex commissioning requirements to reach commercial operation efficiently. FlexGen leveraged its HybridOS energy management system and One Touch Commissioning approach to streamline project execution and accelerate operational readiness. Despite being ten times larger, the FlexGen-supported project reached commercial operation months ahead of the smaller project, demonstrating how an effective commissioning approach can shorten project timelines and accelerate the path to revenue. What You'll Learn How One Touch Commissioning reduces deployment risks and streamlines project execution. How pre-deployment testing accelerates utility-scale BESS commissioning. How accelerated commissioning shortens time-to-revenue and supports project economics. View Case Study Enter your contact information below to view this case study You must have JavaScript enabled to use this form. First Name Last Name Job Title Industry Industry Academic C&I Consulting Firm Data Center Developer Engineering Firm EPC Financial Institution Government IPP Law Firm Manufacturer Media Munis and Co-Ops Oil & Gas Real Estate Software Transportation Utilities Company Company Email Phone We care about your privacy. Read our privacy policy.